Sizewell C – “Never again”, then why not stop now?

10 Min Read
The Public Accounts Committee says the UK must never again be put in Sizewell C's position, with consumers and taxpayers carrying the risk while private investors are protected. Steve Thomas argues the logical conclusion is to cancel now: just £8.7bn has so far been spent, compensation is capped, and abandonment would spare electricity consumers £58–98bn over the plant's 60-year life.
Stephen Thomas
- Emeritus Professor of Energy Policy
| Greenwich University

1. Introduction

The UK Parliamentary Public Accounts Committee (PAC) delivered a devastating verdict on the deal to build, own and operate the Sizewell C nuclear power plant.1

“Sizewell C represents a terrible deal for the UK taxpayer. Successive governments’ failure to deliver new nuclear has left the UK in a position where the best terms it could secure to deliver Sizewell C mean that consumers and taxpayers shoulder significant financial risks, while private investors enjoy protected profits. The UK must never be put in this position again.”

The deal for Sizewell C contained three cost and construction time estimates. There is a target construction cost of £38bn, the Sizewell C management estimate, but with no estimate of completion date. The Lower Regulatory Threshold (LRT) of £40.5bn with completion at the end of 2039 was described by government as its “central estimate”. There is a Higher Regulatory Threshold (HRT) of £47.7bn with completion in November 2043 which government described as a “remote” possibility.2 The PAC report notes that the Taishan project in China for two EPRs was five years late and 60% over budget. The Taishan project is widely portrayed as being a demonstration that EPRs can be built successfully. Simon Bowen, then Chair of Great British Nuclear, told the Energy Security and Net Zero Committee that Taishan was what “everybody says is a fantastic build”.3

It is hard to see how a cost and time overrun of 18% and four years can be described as a remote possibility when the most successful EPR project was 60% over budget and five years late.

The report contains many examples of how the deal is a poor one for taxpayers. For example, the Report states:

“This sharing of risk with consumers means that as project costs increase from the lower regulatory threshold to the higher regulatory threshold, private investors will only have to provide an additional £30 million while consumers will pay an additional £9.8 billion during the construction period and an additional £12 billion over Sizewell C’s 60-year operating life in real terms.”4

Unfortunately, the report was published on Budget Day, 28 October 2026, so any publicity it attracted was short-lived and the questions it raised were not subject to any substantive debate.

The main questions raised are:

  1. Given that Sizewell C is still three or more years from main construction, marked by first nuclear concrete, should the option of abandoning this “terrible” deal be investigated?
  2. It is clear that the deal that led to the construction of the Hinkley Point C station, often known as the Contracts for Difference (CfD) model is not repeatable and the PAC’s verdict on the Sizewell C deal, financed through the Regulated Asset Base (RAB) model, is that the UK “must never be put in this position again”. Given this, what finance models are there for subsequent nuclear projects?
  3. Is national public ownership appropriate for nuclear power plants?
  4. Are the PAC’s recommendations for making it easier to build a finance package for UK nuclear power plants realistic?

2.  Should Sizewell C be abandoned?

Main construction of the Sizewell C project is not expected to start until around 20295 so the money spent so far is only a small fraction of the plant’s expected construction cost of £40.5bn. By contrast, we have estimated the additional costs that will fall on consumers from being forced to buy the output of the plant for the 60-year contract length are in the range £58-98bn, compared with buying the same output at about £90/MWh, the highest successful bids in the latest renewables auction.6 So, even if the plant is built on time and to cost, the costs of abandonment will represent only a small proportion of the savings made by not going ahead.

Given the UK’s record of continuing to pour public money into projects long after it was clear they were doomed to failure – Concorde, the Advanced Gas-cooled Reactor programme of the 1960s, and most recently HS2 – the government must learn from these failures; it should swallow its pride and abandon Sizewell C.

2.1.  Cancellation costs

The PAC report states that “a discontinuation and compensation agreement that would provide up to £70 billion from government if the project is closed or the facility is permanently shut down and Sizewell C Ltd is not at fault.”7 The NAO explains that this compensation, which covers political risks, is capped at the value of the regulated asset base, which is expected to peak at around £70bn at the HRT.8 However, if the project were cancelled now, the cap would be the far smaller value of the asset base at that point: by the end of 2025/26, Sizewell C had spent £8.7bn.9

The contribution of private investors to the funding of construction is very small. Ofgem’s indicative assumption is that an efficient nuclear licensee would be financed by 65% debt and 35% equity.10 On that basis, if the project is built for the LRT figure of £40.5bn, the equity put in by non-government investors (55.1%) would be about £8bn. However, the consumers’ surcharge in the construction period provides about 60% of this, meaning private investors only have to provide about £3bn of their own cash.11 The debt will be lent to Sizewell C Limited by the UK taxpayer-funded National Wealth Fund (NWF) up to £36.6bn12 and a consortium of 13 banks will lend about £5bn, guaranteed by the French state-controlled Bpifrance, to finance work done by EDF and other French contractors.13 The consumers’ surcharge pays all the finance costs for these loans in the construction period, so there is no cost to the private investors and if the project was cancelled, any NWF loans would have to be largely written off. Some contracts have already been signed and cancelling them is likely to incur penalties. Compensating private shareholders and commercial lenders, and paying those penalties, might cost about £6-7bn, of which about £4.8bn would go to private shareholders; the basis for these figures was set out in an earlier Policy Brief.14 There would also be the cost of restoring the site, likely to be under £1bn.

If costs are higher than the LRT, the PAC report makes it clear that investors will only have to contribute a tiny proportion of these additional costs up to the HRT. If costs exceed the HRT, private investors are not contractually obliged to offer further finance and it is difficult to see why they would volunteer to bail out a failing project. The PAC records DESNZ as saying investors would face “very bad dilution” if they did not fund above the HRT.15 However, since the return on what they have already invested is unaffected no matter how diluted their percentage stake becomes, this is unlikely to be a matter of concern to investors. In Centrica’s presentation on its investment in Sizewell C, it states, “Above HRT: no impact on Centrica RAB.”16

Effectively, this means the private investor contribution is capped at their share of the LRT estimated cost. If the asset base were £40.5bn and the allowed real return 5%, the non-government investors (55.1%) would expect to earn up to about £1.2bn a year once the plant is operating.

The total cost of abandonment is therefore dwarfed by the additional costs consumers will be forced to pay over the life of the contract of £58-98bn. The sooner the project is cancelled, the sooner consumers will be able to stop paying the consumers’ surcharge on their electricity bills. Consumers have been paying the surcharge since December 2025: £3.66/MWh in its first full quarter (January-March 2026) and £3.68/MWh for January-March 2027.17 Because consumers pay a return on everything spent, it will rise as construction spending grows and will continue until three years after Sizewell C enters commercial service.

3.  How might future UK nuclear projects be financed?

The problem with finance is that nuclear projects are inevitably a major economic risk because, in the OECD countries, they invariably overrun their construction cost and time estimates, usually by a substantial margin. The nuclear industry tries to deflect blame by citing obstructive and bureaucratic regulatory and planning processes claiming the risks would be substantially reduced by streamlining these processes and committing to large scale standardised ordering programmes. There is no evidence to support these assertions and the more plausible explanation is that these delays, especially with the EPR, are the result of the increasing complexity of nuclear plants brought about by the need to address safety weaknesses revealed by accidents such as those at Chernobyl and Fukushima. In 2022, a former CEO of EDF, Henri Proglio, told a French National Assembly inquiry that the EPR, the design being built at Hinkley and proposed for Sizewell, is “an overly complicated”, “virtually unbuildable machine”.18

The PAC report notes that of the four EPR projects that have progressed beyond start of construction,19 “Flamanville 3 in France is currently around 14 years behind schedule and has experienced cost increases of approximately 300%, Olkiluoto 3 in Finland suffered 14 years of delay and came in 320% over budget, and Hinkley Point C in the UK is currently 5 to 7 years delayed and around 100% over budget. Taishan 1 and 2 in China were each delayed by 5 years and collectively exceeded their estimated budget by 60%.”

The issue will not be solved by adding incentives and short-circuiting essential regulatory processes. The issue is who can and should bear the risk. Logically, it should be the supplier of the technology. This was tried at the Olkiluoto EPR project in Finland where the vendor, Areva NP (the former name of Framatome) agreed to supply the plant at a fixed price regardless of what the actual cost was. The losses to it on this deal contributed significantly to the financial collapse of Areva in 2017. For Hinkley Point C, EDF agreed a fixed power purchase price via a Contract for Difference (CfD), again, regardless of what the construction cost was. In February 2024, EDF wrote off €12.9bn of its investment in Hinkley Point C with the likelihood that further write-offs will be required if costs escalate further. This CfD model works well for offshore wind because the economic risk is low enough that suppliers are willing to take it. However, it can clearly not be used again for a nuclear project because the nuclear risk is far too high.

For Sizewell C, it is the public that is bearing the risk via the RAB model and the PAC states “The UK must never be put in this position again.” As with the CfD model, it is nuclear technology that is the problem not the financial model. The RAB model was used, apparently successfully, with the Thames Tideway project. However, the difference is that with Thames Tideway, there were several competing consortia all willing to take on a significant proportion of the project risk. That was possible because a sewer tunnel is well-understood engineering; with the EPR, no one but EDF was offering to build it, and investors could set their terms. For Sizewell C, there was no question of competing consortia and a deal was only possible, albeit with terrible terms, because the government took nearly half the equity. It also had to placate consumers by recycling its profits back to electricity consumers so that its equity contribution of about £6.4bn20 will represent an investment of taxpayers’ money that will earn no return whatsoever.21

The simple answer is that a new deal for a nuclear project, cloaked no doubt in obscure jargon, will not be possible. If the risk falls on investors, they will not invest and if it falls on the public, they should not be asked to take it.

4.  Is public ownership of nuclear power plants appropriate?

The new nuclear programme launched after the Blair government’s 2006 Energy Review, and the aim of 16GW nuclear generating capacity that followed, was only politically possible because of a promise that there would be no public subsidies and no public ownership. There has been almost a 180-degree turn since then with nuclear deals requiring huge public subsidies and an increasing financial role for the State.

In the previous section, we argued that the lessons from the Hinkley Point and Sizewell deals are that bringing in private investors is now either infeasible or unacceptable. This leaves public ownership as the only option and while the Wylfa SMR project is being developed by the government-owned Great British Energy – Nuclear and its final ownership structure has yet to be determined, it is hard to see how it could be anything other than majority, or 100% public ownership.

There are cases for public ownership, for example, with an infant industry or with a politically vital capability. However, nuclear power does not meet either of these criteria. Using public money to invest in a technology that the private sector will not go near without massive public subsidies and guarantees is not a good rationale for public investment.

5.  Can the UK build a good enough reputation in nuclear construction?

The PAC’s recipe for solving the problem of how to finance new nuclear in the UK is:

“(T)he Department should set out how it will build confidence that future investment in UK nuclear power infrastructure can offer secure and predictable returns, so the financial risks of any future schemes, including small modular reactors, can be distributed more fairly, and provide a stronger link between investor returns, project delivery performance and investor risk exposure. This should include how it plans to put in place the necessary conditions to reduce the nuclear premium investors charge towards zero for future projects.”

This begs at least two questions:

  1. Is it the UK’s poor record with nuclear projects that makes financing nuclear projects in the UK so difficult?
  2. If it is, and the UK’s reputation can be rescued, when might it be possible to bring private finance for nuclear projects on acceptable terms?

The lack of confidence in nuclear projects is not based on UK experience alone. Hinkley Point C is about six years late and running at nearly 100% over budget. France is often seen as the world expert in nuclear technology however, its recent experience appears worse than that of the UK. The Flamanville 3 project only entered service briefly in May 2026, nearly 19 years after construction started, before being taken out of service for repairs; its cost is running at several times the forecast. The four previous French reactors, the N4 units at Chooz and Civaux, completed in 2000-02, took 11-16 years from the start of construction to commercial operation.22 The market will judge the risk of nuclear projects on a global basis not on the record in the UK.

There are currently three firm nuclear projects in the UK. The Hinkley Point C project has already gone far too badly for it to do anything but damage to the UK’s reputation. If the Sizewell C project goes to plan, it will come online around 2040 at a cost of about £40.5bn. Such a long timescale is hardly likely to impress financial institutions. An investment decision is not expected to be taken on the Rolls-Royce SMR project for Wylfa before 2029. This means first power is not likely before the mid-2030s. One successful project is unlikely to change the perceptions of financiers; it would take a series of smoothly executed projects. However, unless the UK makes a reckless decision to order more Rolls-Royce SMRs before the technology is fully and successfully demonstrated, follow-on orders would not come online until well after 2040.

It is an unacceptable risk for the government to bet the reliability of the UK’s electricity supplies and its ability to meet climate change targets on such a distant and speculative outcome.

6.  Conclusions

The case to abandon Sizewell C now before even more public time and money is wasted is overwhelming. However, there appears to be no appetite in Parliament or the media to pose the more general question, whether a significantly expanded nuclear component is an essential element for a decarbonised, reliable British electricity system. This is despite the huge cost of new nuclear, the likelihood that a high proportion of projects announced will fail to be built and that an expansion of nuclear capacity above current levels is not possible before 2040. It is not the PAC’s job to ask that question; that falls to the Energy Security and Net Zero Committee. Its report on the nuclear roadmap, published on 20 November 2026, does not ask it either. The Committee is “persuaded by the need for an expanded role for nuclear power”, yet accepts that the RAB model transfers “significant construction risk from investors to consumers” and recommends that future large projects should not be financed through new consumer levies unless the government can show this is better value than general taxation.23 It does not mention the PAC’s verdict, published days before it agreed its report, nor does it consider whether Sizewell C should go ahead.

It is the pursuit of nuclear power that is raising power prices, jeopardises Britain’s ability to meet its emissions target and risks our future security of supply. The PAC report provides the ammunition to launch such a debate and it is essential this opportunity is taken.


1. Committee of Public Accounts, Sizewell C, Seventeenth Report of Session 2026-27, HC 106 (London: House of Commons, 28 October 2026).

2. Department for Energy Security and Net Zero, Sizewell C (SZC) Final Investment Decision: Value for Money (VfM) Assessment (London: DESNZ, July 2025), 8, https://assets.publishing.service.gov.uk/media/687f951dfdc190fb6b84689d/szc-fid-vfm-assessment.pdf.

3. Energy Security and Net Zero Committee, Oral evidence: Work of the Department for Energy Security and Net Zero, HC 396, 20 November 2024, Q46 (Simon Bowen), https://committees.parliament.uk/oralevidence/15023/html/.

4. PAC, Sizewell C, para 15.

5. Sizewell C Ltd, Annual Report and Accounts 2025-26, 5, https://www.sizewellc.com/wp-content/uploads/2026/07/Annual-Report-2025-26.pdf.

6. Stephen Thomas, “To Fund the Burnham Government’s Priorities, Abandon Hinkley Point C, Sizewell C and Wylfa,” Policy Brief, October 2026, https://policybrief.org/briefs/to-fund-the-burnham-governments-priorities-abandon-hinkley-point-c-sizewell-c-and-wylfa/.

7. PAC, Sizewell C, para 16.

8. National Audit Office, Sizewell C, Report by the Comptroller and Auditor General, HC 33, Session 2026-27 (London: NAO, 20 May 2026), para. 2.15, https://www.nao.org.uk/reports/sizewell-c/; Michael Shanks, Parliamentary Under-Secretary of State for Energy Security and Net Zero, “Departmental Contingent Liability Notification: Sizewell C Funded Decommissioning Programme and Government Support Package,” written statement HCWS893, House of Commons, 1 September 2025, https://questions-statements.parliament.uk/written-statements/1830407.

9. Sizewell C Ltd, Annual Report and Accounts 2025-26, 19, https://www.sizewellc.com/wp-content/uploads/2026/07/Annual-Report-2025-26.pdf.

10. Ofgem, Our Approach to the Economic Regulation of Sizewell C (London: Ofgem, August 2025), 50, para 4.51, https://www.ofgem.gov.uk/sites/default/files/2025-08/Our-approach-to-the-Economic-Regulation-of-Sizewell-C.pdf.

11. Stephen Thomas, “Sizewell C – The Last of Its Kind,” Policy Brief, December 2025, 6, https://policybrief.org/wp-content/uploads/2025/12/Sizewell-C-%E2%80%94-The-last-of-its-kind.pdf.

12. National Wealth Fund, “Sizewell C,” factsheet (London: NWF, 2025),  https://www.nationalwealthfund.org.uk/media/hzid05lp/factsheet-sizewell-c-174aef5b76fc460e81571fc4ec6ff6e8.pdf.

13. Bpifrance, “France Supports Sizewell C with £5bn Loan Guarantee,” 23 January 2026, https://www.bpifrance.com/2026/01/23/france-supports-sizewell-c-with-5bn-loan-guarantee/.

14. Thomas, “To Fund the Burnham Government’s Priorities,” using the Sizewell C Annual Report 2025-26, 5 and 19.

15. PAC, Sizewell C, para 18.

16. Centrica, Sizewell C (investor presentation, 2025), slide 22, https://www.centrica.com/media/cfwb43au/centrica-2025-sizewell-c-presentation.pdf.

17. The surcharge (the nuclear RAB Interim Levy Rate) started at £3.494/MWh in December 2025 and was £3.663/MWh for January-March 2026. The rate for October-December 2026, £3.754/MWh, was raised to £5.151/MWh from 6 December 2026 to recover a shortfall for that quarter. Low Carbon Contracts Company, “Nuclear Regulated Asset Based Bulletin,” 7 November 2025, https://www.lowcarboncontracts.uk/news/nuclear-regulated-asset-based-bulletin/; Low Carbon Contracts Company, “In-Period Adjustment to Nuclear RAB Interim Levy Rate from 6 December 2026,” EMR Settlement, 6 November 2026, https://www.emrsettlement.co.uk/in-period-adjustment-to-nuclear-rab-interim-levy-rate-from-6-december-2026-2/; Low Carbon Contracts Company, “ILR and TRA for the Nuclear Regulated Asset Base Scheme for Q1 2027 Determination,” 27 October 2026, https://www.lowcarboncontracts.uk/news/ilr-and-tra-for-the-nuclear-regulated-asset-base-scheme-for-q1-2027-determination/.

18. Henri Proglio, evidence to the Commission d’enquête visant à établir les raisons de la perte de souveraineté et d’indépendance énergétique de la France, Assemblée nationale, 13 December 2022, in Rapport d’enquête n° 1028, tome 2 (Paris: Assemblée nationale, 30 March 2023), https://www.assemblee-nationale.fr/dyn/16/rapports/ceindener/l16b1028-t2_rapport-enquete.

19. PAC, Sizewell C, para 6.

20. We assume the construction cost is £40.5bn with the government 44.9% stake costing £18.2bn of which 35%, £6.4bn, will be equity, based on Ofgem’s notional 65/35 debt-equity assumption (see note 10).

21. National Audit Office, Sizewell C, HC 33 (London: NAO, 20 May 2026), paras 1.22 and 2.17; email from Ofgem to Policy Brief, 7 November 2025.

22. International Atomic Energy Agency, Country Nuclear Power Profiles: France (Vienna: IAEA, 2020), Table 5, data from the IAEA Power Reactor Information System (PRIS), https://www-pub.iaea.org/MTCD/Publications/PDF/cnpp2020/countryprofiles/France/France_tables.htm.

23. Energy Security and Net Zero Committee, Revisiting the Nuclear Roadmap, Sixth Report of Session 2026-27, HC 233 (London: House of Commons, 20 November 2026), summary and paras 85-89.

Share this Brief

LinkedIn
Facebook
Twitter
Telegram

Meet Our Contributor

Stephen Thomas
Emeritus Professor of Energy Policy
Greenwich University
contact@policybrief.org

Related Briefs

London,,United,Kingdom,-,September,09,2026.,British,Prime,Minister
20 Min Read
Stephen Thomas
| Greenwich University
Britain’s three new nuclear projects – Hinkley Point C, Sizewell C and Wylfa – now depend on public money, above all from the National Wealth Fund, which has committed up to £36.6bn to Sizewell C alone: about twice what it can lend to all its other projects. Abandoning all three would save consumers £93–133bn and free the NWF to back renewables, energy storage and the government’s regional and industrial priorities.
Civil and nuclear pic
6 Min Read
Andy Stirling
| Science Policy Research Unit (SPRU), University of Sussex
Phil Johnstone 
| Global Studies, University of Sussex
The government's nuclear deregulation drive rests on assumption, not evidence, never comparing nuclear with cheaper, faster alternatives, downplaying safety risks, and denying trade-offs outright. A less visible driver, they suggest, is military pressure: sustaining Britain's submarine-building base costs over £5 billion a year.
Water,Pipeline,To,Hydro-electric,Power,Station,At,Tarraleah,,Tasmania
10 Min Read
Pete Roche
At the end of June 2026, Ofgem's decision on government support for Long Duration Energy Storage backed 16 projects (7.6GW), nearly tripling Britain's storable electricity — but stuck largely to large-scale pumped hydro and lithium-ion batteries. With battery costs falling fast and nuclear growing costlier and more delayed, there is a strong case for even more energy storage using a wider range of emerging technologies and hydrogen in the near future.
The unbeatable combination of renewables and batteries-resized-to-2560x1707 (1)
8 Min Read
David Toke
| University of Aberdeen
Batteries are transforming electricity markets — and fast. Plummeting costs, driven by the EV revolution, are making renewables-plus-batteries cheaper than gas across much of the world. California and Australia are already demonstrating how grid-scale batteries can reshape electricity supply, shifting solar generation to meet evening peaks. The UK is expanding capacity but risks missing its 2030 targets. One bottleneck dominates: grid connection queues. The unbeatable combination of renewables and batteries is coming — the only question is how fast.
The Nuclear Regulatory Taskforce- The wrong questions, the wrong team, the wrong answers
30 Min Read
Stephen Thomas
| Greenwich University
The 2025 Nuclear Regulatory Taskforce was set up to cut “red tape”, with terms of reference that signalled the answers wanted. Stephen Thomas finds the diagnosis wrong. Five of the six projects launched after 2006 failed for want of investors and finance, not planning or regulation, and Hinkley Point C’s overruns owe more to the EPR design. None of the five members had expertise in radiation science or the environment, or had built or operated a nuclear plant. Yet the…
Electricity,Pylon,Overhead,Power,Line,Transmission,Tower,At,Sunset.
7 Min Read
David Newbery
| Faculty of Economics, University of Cambridge
The UK's clean energy transition requires massive grid investment, but plans inherited from asset-hungry National Grid are proposing unnecessarily expensive subsea transmission links. Cambridge economist David Newbery argues that onshore HVDC cables and better pricing signals for wind farm locations could save billions. NESO must revisit its Beyond 2030 report, and Ofgem must ensure transmission charges truly reflect the cost of new connections.
London,,United,Kingdom,-,July,23,,2024:,Ed,Miliband,,Britain's
12 Min Read
Pete Roche
Long Duration Energy Storage (LDES) is emerging as the critical missing piece in UK energy policy, with energy group Iberdrola calling it the "key enabler for a 100% renewable electricity grid". New long-duration battery technologies as well as a diverse range of other energy storage technology is coming forward, but UK Government plans for only 4-6GW of capacity are not ambitious enough.
How the sun went down on UK nuclear
20 Min Read
Stephen Thomas
| Greenwich University
The UK governments have been keen to pursue nuclear power projects since 2006, but it has been stop and go.  In 2016, the government moved forward on small modular reactors, only to shelve plans before starting again in 2021.  Since then, one Small Modular Reactor has been chosen and the final investment decision is expected by government in 2029. This is unlikely given delays in process and the fact that it is yet to be determined who will own the plant, how…
The Government is onto a false trail on the UK's nuclear troubles
10 Min Read
Stephen Thomas
| Greenwich University
The idea that the UK is uniquely poor at building nuclear power plants is not supported by the evidence. Reports identifying that the dominant causes of these delays and high costs are due to slow and obstructive planning and regulatory processes are not proven. The UK’s track record is very much in line with nuclear projects in comparative countries – Finland, France and the US. Understanding the real causes of cost overruns and delays would provide a far better basis…
small-modular-reactors-game-changer-or-more-of-the-same
7 Min Read
Stephen Thomas
| Greenwich University
There has been a large amount of publicity on Small Modular Reactors (SMRs) based on exaggerated, unproven or untrue claims for their advantages over large reactors. Only one order for a commercially offered design has been placed (Canada) and that had yet to start construction in January 2026. The UK should not invest in SMRs until there is strong evidence to support the claims made for them.

Email A Letter To Our Editor